Large-Load Cost Table

What a 50 MW connection costs and takes in 15 US markets: study fees, security per MW, minimum bills, contract terms, exit fees and realistic energization year, from tariffs and dockets.

realistic energization year for a new 50 MW load in Northern Virginia, Dominion Energy, from a 2026 application. Public headline as of August 21, 2026.

$75M
Collateral for 50 MW under Dominion Schedule GS-5 at $1.5 million per MW, LBNL and Brattle brief, August 10 2026
14 years
Dominion GS-5 minimum term including a four-year ramp; AEP Ohio DCT up to 12; Georgia Power up to 15
85%
Minimum bill as a share of contract demand, Dominion GS-5 (distribution and transmission) and AEP Ohio DCT cap
15
Markets side by side, each cell linked to the tariff sheet, PUC order or ISO document it came from

What it covers

Fifteen US markets for a 50 MW connection: Northern Virginia (Dominion), Columbus (AEP Ohio), Atlanta (Georgia Power), Dallas-Fort Worth (Oncor), Houston (CenterPoint), West and South Texas (AEP Texas), the Carolinas (Duke), Phoenix (APS and SRP), Salt Lake City (Rocky Mountain Power), Louisiana (Entergy), Colorado (Xcel), Chicago (ComEd), the Bay Area (PG&E) and Northern Indiana (I&M). For each: MW threshold, whether the rule applies at 50 MW, study fee, security or collateral in dollars, minimum bill, contract term, ramp, exit fee, CIAC exposure and the realistic energization year with its basis.

Cadence
Updated as dockets move; reviewed monthly; energization years revisited each quarter
Compiled from
Utility tariff sheets and PUC orders (Virginia SCC PUR-2025-00058 and PUR-2026-00056, PUCO 24-508-EL-ATA, Georgia PSC docket 55378, PUCT Projects 58480 and 58481, Oregon PUC Order 26-154, CPUC D.25-07-039); ERCOT large-load status decks; PJM BRA results; the LBNL and Brattle large-load rate-design brief (August 2026); EIA industrial rates by state; JLL Global Data Center Outlook 2026 for time to power
Delivered as
Excel workbook, Web dashboard
Updates
Quarterly updates, one year included
Onboarding
Onboarding call
Support
Ad hoc analyst calls
Tier
Table free; history Pro; alerts Institutional

Who uses it and what it decides

  • Datacenter developers and site selectorsWhich market energizes first, what the deposit per MW is, and how much cash a portfolio has locked in security.
  • Factory owners adding 20 to 100 MWWhich regime a plant expansion lands in (below Texas's 75 MW, above AEP Ohio's 25 MW, inside Georgia's 100 MW rule) and what that costs.
  • Lenders and investorsMinimum-bill and exit-fee exposure over a 12 to 15 year term, market by market.

Methodology

What the headline is

2033 is the year a 50 MW load applying to Dominion Energy Virginia in 2026 can realistically expect to energize. The basis is JLL’s Global Data Center Outlook 2026 (p.18), which puts Northern Virginia at about seven years to power for a new 50 MW site, and Dominion’s own load pipeline of about 70 GW against a 24.6 GW system peak as reported by Utility Dive in February 2026. The shortest markets in the table (Houston, Northern Indiana, Salt Lake City) are 2028 to 2029. The full column with its basis is in energization-years.csv.

The headline is the longest realistic energization year among the 15 markets. It moves when a utility publishes a schedule that changes it.

What it is compiled from

Version 0.1 is tariffs, orders and ISO documents. No developer interviews yet.

Every cell prints its verification status: VERIFIED against the primary document, or SECONDARY with the outlet named.

What is free and what is paid

  • Free: the 15-market table as published in What 50 MW Costs in 15 US Markets, this page, and the Large-Load Interconnection Cost calculator with default inputs.
  • Pro: the table’s history as dockets move, the 20 MW and 100 MW scale factors, and the minimum-bill cash schedules by market.
  • Institutional: the workbook and dashboard, docket alerts when a cell changes, custom markets, quarterly updates for a year, an onboarding call and ad hoc calls.

Articles built on it

What 50 MW Costs in 15 US Markets, The 2 MW Plant Service Upgrade Nobody Budgets Right, A Factory Owner’s Guide to the PJM Capacity Charge and Datacenter Construction Is Eating Your Electricians. The rule calendar lives on the Large-Load Policy Tracker.

Version history

  • 0.1 (August 2026). Fifteen markets. Tariffs and orders through 20 August 2026 (PUCT good-cause exception for ERCOT). Study fees and exit-fee amounts not published for Dominion; cells say so.

What version 1 adds

Developer interviews on actual study outcomes and actual energization dates against the tariff’s promise, and the utility’s study-queue position where a utility publishes one. Interview counts print here only when true.

Known gaps

Dominion’s study fee and exit-fee amounts were not in the sources opened. CenterPoint and ComEd security figures are implied averages from company statements (about $64,000 and $250,000 per MW), not tariff sheets, and are marked as such. Texas’s $50,000 per MW security is a proposed rule and does not apply at 50 MW; the table carries the 75 MW case beside it.

Questions

Why 50 MW?

It is the size most new tariffs are written around (median threshold 25 MW across 55 tariffs in the LBNL and Brattle brief) and it sits under Texas's 75 MW line, which makes the regimes comparable. Scale factors for 20 and 100 MW are in the Pro table.

How is the energization year chosen?

From the utility's or ISO's own statements where they exist (ERCOT Batch Zero dates, CenterPoint's 2029 plan, AEP Ohio's contract schedule) and from JLL's 2026 market-by-market time-to-power figures where they do not. The basis is printed beside every year.

Does the table include the capacity charge?

PJM markets carry the BRA clearing price ($333.44 per MW-day for 2027/28, $325.00 for 2028/29) as a separate column. The PJM Capacity Charge Estimator does the bill arithmetic.

Free calculators built on this model

  • Large-Load Interconnection Cost

    MW and market to study fees, security deposit, minimum-bill exposure and realistic energization year, from the Large-Load Cost Table.