PowerDraft
What 50 MW Costs in 15 US Markets
Dominion $1.5M per MW and 14 years, AEP Ohio 72.5% minimum at 50 MW.
Low-voltage switchgear (LVDO), made to order. Source: Schneider Electric Lead Times Guide, September 2026 edition, published 2 September 2026. Eleven classes tracked; class detail is Pro. Sep 2026.
50 weeks, LV switchgear, published lead time, Schneider Electric Lead Times Guide, September 2026 edition. Monthly, first business day, after the Schneider guide (about the 2nd) and the M3 release.
Open the Lead-Time MonitorLead articleProcurementDraft
IEEPA struck down Feb 20Section 122 ran to Jul 24Section 301 forced-labor tariffs on 60 economiesSection 232 metals at 50/25/15/10 with the Annex III 15% tier to Dec 2027.
Prannay Hebbar, September 9, 2026. 18 minute read, free to the paywall.
PowerDraft
Dominion $1.5M per MW and 14 years, AEP Ohio 72.5% minimum at 50 MW.
ProcurementDraft
Cap norms by equipment class, what a week of delay costs per MW.
ProcurementDraft
Ocala's $1.1M PPI escalator, LDs at $250 a day capped at 5%.
PowerDraft
Oncor's 298 GW of requests, Batch Zero.
ProcurementDraft
Base price, copper escalator.
MachineryDraft
USMTO $3.44B in H1 2026, units down 2.6%.
50weeks
LV switchgear, published lead time, Schneider Electric Lead Times Guide, September 2026 edition
Published lead times for eleven equipment classes compiled from OEM lead-time guides, Census M3 unfilled orders over shipments, ISM supplier deliveries and backlog disclosures in filings. Every cell carries its OEM and date.
3.0x
Powell Industries book-to-bill, quarter ended June 30 2026: $934M of orders on $312M of revenue
Quarterly orders, backlog and book-to-bill for every listed electrical, power and cooling OEM, from filings only, with the read-across for buyers: which classes are getting longer and which are clearing.
$9.8Mper MW
all-in datacenter build cost, Phoenix and Columbus, Turner & Townsend Data Centre Construction Cost Index 2025
Capex per MW by component on the Turner & Townsend and JLL baselines, air-cooled and liquid-cooled, with each line's lead time from the Lead-Time Monitor and the carrying cost of delay.
Latest copper price to $/ft of metal by NEC conductor size, with an escalation-clause calculator for bids.
Open the calculatorTen-year cost of a standby or prime generator set: diesel vs gas vs dual fuel, fuel, maintenance, permitting, Tier 4 aftertreatment, run hours.
Open the calculatorMW and market to study fees, security deposit, minimum-bill exposure and realistic energization year, from the Large-Load Cost Table.
Open the calculatorEvery article is free to the paywall. Pro opens the rest, plus the vendor-level detail and the calculators with saved inputs. Desk and Institutional are for teams who want the alerts and the data itself.